Listen to this article
O project replacement of Terminal A at Newark-Liberty International Airport is facing a complex legal dispute between two companies key. You will read about the battle between the consortium Tutor Perini/Parsons and the subcontractor STV Engineering. They dispute responsibility for costs with differences on how to count the deductible in insurance. A judge ruled that this discussion should be resolved through arbitration before other legal issues can be dealt with. The situation is an example of how conflicts in large construction projects can quickly turn into problems difficult legal issues.
- Project US$ 2.1 billion at Newark Airport creates complex legal disputes.
- Tutor Perini/Parsons sued STV for extra costs due to design errors.
- A judge has ruled that it is necessary to arbitrate the issue of deductible of US$ 1 million.
- STV claims it made no mistakes, while Tutor Perini/Parsons attributes costs to STV.
- Disputes lead to lawsuits involving significant legal costs for both parties.
The Complex Construction Conflict at Newark Airport
The Terminal A Project
Did you know that the project to replace Terminal A at Newark-Liberty Airport, which costs US$ 2.1 billionhas turned into a real legal nightmare? The companies involved, the joint venture Tutor Perini/Parsons and STV Engineering, are in the middle of a dispute involving million dollars. What began as a construction project is now filled with legal discussions e accusations.
What's at stake
Tutor Perini/Parsons, the main contractor, sues STV for additional costs arose due to design errors. These errors were pointed out by subcontractors working on the project. A federal judge has ruled that, before resolving this issue, the companies need to go through a arbitration about how many deductible from US$ 1 million each must pay its insurance. This insurance, from Lexington Insurance Co., covers damages and defense costs, but only up to a limit of US$ 25 million by complaint.
The role of the judge
Judge Linda S. Jamieson ruled that STV's complaint, which asks Tutor Perini/Parsons to start paying STV's legal costs, about US$ 85,000 so far, should be suspended. It wants the arbitration on deductibles to be concluded first. AIG, Lexington's claims administrator, says that there are seven complaints in total, which would mean that the insurance company should receive US$ 7 million before starting to cover the costs. On the other hand, both Tutor Perini/Parsons and STV believe that only the following should be considered a complaint.
The Deductibles Dispute
The central question is who should pay deductible. Tutor Perini/Parsons argues that, according to the insurance contract, STV should bear this, while STV points to clauses in its contract that say Tutor Perini/Parsons is responsible. This confusion could lead to a complicated impasse.
What Caused the Dispute?
This dispute seems to be the result of a project of design-build complicated, where costs are higher than expected. Usually, when something goes wrong, the contractor blames the designer. In this case, the designer is a subcontractor, making things even more complicated. In January 2023, Tutor Perini/Parsons sued STV, seeking to US$ 99 million in additional costs due to errors and overdesigns.
Design mistakes
STV, based in New York City, had a basic engineering contract of US$ 58 million. However, Tutor Perini/Parsons claims that STV issued 200 communications to correct its own design errors in areas such as electrical, HVAC (heating, ventilation and air conditioning), plumbing and fire protection. These errors, according to the joint venture, caused significant additional costs for subcontractors.
Additional costs
Tutor Perini/Parsons argues that STV has added US$ 72 million in costs due to errors and omissions, US$ 20 million related to overdesignsand more US$ 5 million due to deficiencies in the BIM (Building Information Modeling) model. These figures can increase rapidly and affect the total project budget.
STV's defense
On the other hand, STV denies that it made any mistakes or that it made any overdesigns that increased costs. STV argues that Tutor Perini/Parsons had insurance that covered STV for any liability related to errors. However, in order for the cover to be activated, Tutor Perini/Parsons needs to pay seven deductibles for each of the separate complaints.
AIG's response
In response to the joint venture's request for insurance coverage, Avi Glikman, AIG's director of complex claims, stated that the responsibility for paying deductibles rests with the joint venture. He also mentioned that due to the application of New York State law, previous decisions on how to define separate construction claims must be considered.
STV lawsuit
Recently, STV filed a separate lawsuit against Tutor Perini/Parsons, seeking to have the joint venture pay the legal costs that STV has already incurred in relation to the terminal project. It's a complicated situation and all those involved in the dispute declined to comment or could not be contacted.
Conclusion
In short, the conflict around the project to replace the Terminal A at Newark-Liberty International Airport illustrates how legal disputes can arise in large construction projects. With a total value of US$ 2.1 billionthe battle between the Tutor Perini/Parsons and the subcontractor STV Engineering it's not just a question of costs, but also of responsibilities and design errors. The judge's decision that the deductible must be solved by arbitration before moving on is a reminder that, in complex projects, the legal pitfalls can be as challenging as the construction itself.
If you would like to find out more about topics related to renovation and construction, don't hesitate to visit our website at Renovation Tips. To better understand the challenges faced in large-scale projects, check out how construction work can have an impact on the environment and how managing construction waste.

Adalberto Mendes, a name that resonates with the solidity of concrete and the precision of structural calculations, personifies the union between engineering theory and practice. A dedicated teacher and owner of a successful construction company, his career is marked by a passion that blossomed in childhood, fueled by the dream of erecting buildings that would shape the horizon. This early fascination led him down the path of engineering, culminating in a career where the classroom and the construction site complement each other, reflecting his commitment both to training new professionals and to bringing ambitious projects to fruition.